Airtightness Testing Before Handover: A Project Team Checklist

Blower-door airtightness test set up in the doorway of a tropical building under construction, with a project team checklist

Plan airtightness testing well before handover, not at it. The most useful blower-door test usually happens while the airtight layer is complete but still accessible, so the team can find and repair leaks; a final test near completion then documents the finished enclosure. Agree the target, test method, test scope, responsibilities, and records early, and prepare the building carefully before each test.

Why not wait until handover to test?

By handover, ceilings, wall linings, joinery, and finishes usually cover the membranes, tapes, sealants, and junctions that form the airtight layer. A leak found at that point can mean opening finished work, or accepting a result the team cannot easily improve. The Passive House Institute’s building criteria recommend that the pressure test is carried out when the airtight layer is still accessible so that needed repairs can be carried out.

That is why AllClimate’s airtightness testing service describes a mid-construction test after the airtight layer is installed but before internal linings conceal it, followed by a pre-certification test where a project is pursuing Passive House certification. If you are new to the topic, start with What Is Airtightness and Blower-Door Testing? and come back to this checklist when you are planning the work.

What airtightness target applies?

For the Passive House Standard, the Passive House Institute sets a pressurization test result of n50 ≤ 0.6 air changes per hour at 50 pascals. The current criteria refer to ISO 9972 (method 1) with Passive House–specific provisions, including measurements under both positive and negative pressure; compliance is judged on the average of both. EnerPHit retrofits and the PHI Low Energy Building standard have their own rules, and projects that are not pursuing certification may set a different target in their specifications.

Whatever the target, write it down early: the value, the metric (for example ACH50 / n50), the test method, and how the internal air volume will be calculated. A result means little if the team never agreed what it was measuring against.

Why does airtightness matter in a hot-humid climate?

PAGASA describes the climate of the Philippines as tropical and maritime, with relatively high temperature, high humidity, and abundant rainfall. In that context, uncontrolled air leakage is not only an energy question. Leaks can carry warm, humid outdoor air into the building, add to the cooling and dehumidification load, affect comfort, and create moisture risk where humid air meets cooler surfaces.

Airtightness never replaces ventilation. The Passive House Institute lists airtightness alongside controlled mechanical ventilation with heat recovery among the core principles of its building standards. An airtight building needs a planned ventilation strategy so that fresh air arrives where and when it is intended.

The airtightness checklist

1. During design

  • Agree the airtightness target, test method, and test stages in the project specifications.
  • Show the airtight layer on the drawings. PHI’s certification documents expect detail drawings to indicate the airtight layer and describe how it is executed at connection points.
  • List the planned penetrations: pipes, ducts, cables, conduits, and fixings that cross the airtight layer.
  • Name who is responsible for each junction—window installer, plumber, electrician, mechanical contractor, main contractor.
  • Decide who will test. For Passive House certification, PHI’s criteria exclude people who built the airtight envelope (they would be testing their own work) and the building owner.

2. Before the mid-construction test

  • Confirm that windows and external doors are installed and that membranes, tapes, and sealants are complete at junctions.
  • Seal service penetrations through the airtight layer, or record the ones that are still open.
  • Add the test as a hold point in the construction schedule, before linings, ceilings, or finishes conceal the layer.
  • Keep access for leak investigation. AllClimate’s testing service includes leak detection with infrared thermography and smoke pencil diagnostics.

3. On test day

  • Close exterior windows and doors, and treat intentional openings, such as ventilation intakes and exhausts, exactly as the agreed test method requires. Do not improvise.
  • Switch off cooling units, exhaust fans, and other equipment that moves air.
  • Test the whole conditioned volume. PHI’s criteria state that random measurements of single building parts, or borrowing results from identical buildings, are not enough for certification.
  • Make sure the internal air volume calculation is ready; PHI expects the pressure test report to document the net air volume.

4. After each test

  • Record the result for both pressurization and depressurization, plus the leakage paths found.
  • Assign each repair to a responsible trade, fix it while it is still accessible, and re-test where needed.
  • Photograph the repaired details before they are concealed.

5. At handover

  • Hand over the final test report, photographs of the airtight layer, and the repair log.
  • Tell the owner or facility manager which layer is airtight, so future fit-outs and new penetrations can be sealed properly.
  • File the records where your verification or certification pathway can find them.

Common mistakes to avoid

  • Testing only once, at the end, when leaks are expensive to reach.
  • Letting late service penetrations cut through a layer that already passed a mid-construction test.
  • Leaving the target, method, or volume calculation undefined until the tester arrives.
  • Treating airtightness as optional because the building will be air-conditioned.

How does testing connect to verification?

In PHI’s certification procedure, the final review after construction relies on evidence from the building work, and the criteria name the airtightness test as an example of that evidence. A blower-door result, along with photographs and repair records, helps connect what was designed with what was built. See AllClimate’s Passive House verification page for how that evidence is reviewed.

Where can your project team start?

Book a test discussion through AllClimate’s airtightness testing page. Bring the drawings, the construction programme, and the stage you are at. To build airtightness skills inside your team, review the course modules; the PH1 Building Envelope module covers insulation, airtightness, windows, and thermal bridges.

Frequently asked questions

When should a blower-door test be done?

Ideally at least twice: once mid-construction, when the airtight layer is complete but still accessible for repairs, and again near completion to document the finished enclosure. The right timing depends on the construction sequence and the project’s requirements.

What airtightness value does Passive House require?

For the Passive House Standard, the Passive House Institute sets a pressurization test result of n50 ≤ 0.6 air changes per hour at 50 pascals, based on the average of positive- and negative-pressure measurements. EnerPHit and other standards have their own rules.

Can the contractor who built the envelope carry out the test?

For Passive House certification, no. The Passive House Institute’s criteria exclude parties who were responsible for creating the airtight envelope, as well as the building owner, from carrying out the airtightness test.

Does an airtight building still need ventilation?

Yes. Airtightness controls unintended leakage; it does not supply fresh air. An airtight building needs a planned ventilation strategy, and controlled mechanical ventilation with heat recovery is one of the core principles of the Passive House standards.

Technical source notes

Airtightness criterion, test method, test scope, tester independence, and certification procedure: Passive House Institute, Criteria for Buildings: Passive House – EnerPHit – PHI Low Energy Building, Version 10c (March 2023), PDF hosted by Passive House Network. Core principles of the Passive House standards: Passive House Institute, Building certification. Climate context: PAGASA, Climate of the Philippines. Service details were checked against AllClimate’s airtightness testing and course pages. Entity facts and service pathways were checked against AllClimate Passivhaus’s entity source of truth and live site. Last reviewed 2026-11-16.